Grievance Redress Mechanism (GRM)

The Grievance Redress Mechanism (GRM) provides a formal, transparent, and accessible platform for individuals and communities to raise concerns, complaints, suggestions, or feedback related to project activities, including environmental and social performance.
The GRM is established in accordance with Environmental and Social Standard 10 (ESS10): Stakeholder Engagement and Information Disclosure under the World Bank Environmental and Social Framework (ESF).
The GRM does not replace judicial or administrative remedies. Complainants retain the right to access formal legal systems at any time.

The GRM aims to resolve grievances in a timely, fair, and efficient manner while promoting transparency, accountability, and stakeholder trust.

Specifically, the GRM:

  • Provides accessible avenues for raising concerns
  • Ensures fair and mutually acceptable resolutions
  • Promotes transparency and accountability
  • Identifies systemic issues and corrective measures
  • Reduces reliance on judicial proceedings
  • Ensures affected communities are treated respectfully

The GRM guarantees:

  • Confidential handling of complaints
  • Protection of personal data
  • Non-retaliation against complainants
  • Timely resolution

Two separate GRMs operate under:

  • PIU – Irrigation Department (BID) (Component A)
  • PIU – QWASA (Component B)

Each Project Implementation Unit (PIU):

  • Manages and tracks grievances independently
  • Maintains accessible submission channels
  • Ensures timely resolution
  • Reports GRM performance to the World Bank

Both GRMs are culturally appropriate, widely communicated, and accessible to affected populations.

4.1 Who Can Submit a Grievance?

The GRM is open to:

  • Project-Affected Persons (PAPs)
  • Local communities
  • Workers and contractors
  • Suppliers and vendors
  • Government staff
  • Any interested individual or organization

Anonymous complaints are accepted.

4.2 Issues That May Be Raised

Grievances may relate to:

  • Environmental and social impacts
  • Land acquisition and asset-related matters
  • Labor and working conditions
  • Occupational and community health and safety
  • Labor camps and contractor practices
  • Harassment or misconduct
  • Gender-Based Violence (GBV) / SEA/SH (confidential handling)
  • Conduct of security personnel
  • General project implementation activities

Grievances may be submitted through:

  • Online grievance form
  • Email
  • Phone/SMS
  • WhatsApp
  • Written application
  • Suggestion/complaint boxes
  • In-person submission to designated focal persons

Upon receipt, each grievance is assigned a unique reference number and recorded in the GRM database.

Step 1: Receipt and Registration

  • Grievance recorded in the database
  • Tracking number assigned

Timeline: Within 24 hours of receipt

Step 2: Acknowledgment

  • Written or verbal acknowledgment
  • Complainant informed of next steps and timeline

Timeline: Within 2 working days

Step 3: Screening and Classification

  • Categorization by type and risk level (Low, Moderate, High)
  • High-risk or sensitive cases (e.g., GBV/SEA/SH) handled under special protocol

Step 4: Investigation

  • Site visit (if required)
  • Consultation with complainant (where appropriate)
  • Coordination with relevant departments or contractors

Step 5: Resolution and Response

  • Corrective action, explanation, compensation, or policy adjustment (as applicable)
  • Formal response communicated to complainant

Timeline: Within 15–20 working days from submission

Step 6: Closure

  • Confirmation of complainant satisfaction (where feasible)
  • Documentation and database update

Step 7: Appeal

If unsatisfied, the complainant may submit an appeal to a higher authority or the Project Steering Committee. A final decision is communicated within a defined timeframe.

Step 1: Submission

↓

Step 2: Registration & Acknowledgment (Within 02 Days)

↓

Step 3: Screening & Classification

↓

Step 4: Investigation & Resolution (Within 15 to 20 Days)

↓

Step 5: Communication of Decision

↓

Step 6: Closure

↓

Appeal (If Not Satisfied)

7.1 Component A – Irrigation Department (BID)

PIU-Level Grievance Redress Committee (GRC)

  • Project Director (Chair)
  • Environmental Compliance Expert
  • Gender Specialist
  • Social Safeguard Specialist (GRM Lead / GRO)
  • Representatives from relevant district departments
  • Co-opted members (as required)

The Social Safeguard Specialist serves as the Grievance Redressal Officer (GRO) and is responsible for:

  • Overall GRM coordination
  • Database management
  • Oversight of investigations
  • Reporting to the PIU and the World Bank

District-level Grievance Focal Persons (GFPs) support grievance intake, preliminary review, and communication.

7.2 Component B – QWASA

The GRM is managed by PIU – QWASA through a similar PIU-level GRC structure, including:

  • Project Director (Chair)
  • Environmental Compliance Expert
  • Gender Specialist
  • Social Safeguard Specialist (GRO)
  • Relevant departmental representatives
  • Co-opted members (as required)

Community Focal Points (CFPs) facilitate local access to the GRM in sub-project areas.

For GBV/SEA/SH-related grievances:

  • No written complaint is required
  • Confidential registration with restricted access
  • Immediate referral to qualified service providers
  • Survivor-centered approach
  • No investigation without informed consent

The Project maintains a centralized grievance database to:

  • Track number and types of grievances
  • Monitor acknowledgment and resolution timelines
  • Identify systemic issues and corrective actions
  • Record appeals and pending cases

Quarterly aggregated GRM performance reports (without personal data) are submitted to the World Bank.

In line with ESS10 principles:

  • All grievances are handled confidentially
  • Personal data is protected
  • Anonymous submissions are permitted
  • Retaliation against complainants is strictly prohibited